| |
Appeals
Court of Massachusetts
William
BASTIANELLI
v.
NATIONAL UNION FIRE INSURANCE COMPANY.
No.
93-P-126.
April
21, 1994.
Before
BROWN, SMITH and LAURENCE, JJ.
BROWN, Justice.
The plaintiff seeks to recover for trucking services
provided by him to a subcontractor on a public works
project for which the defendant Modern Continental
Construction Company (Modern) was the general contractor.
The plaintiff advances alternate theories: First,
he alleges that the services were rendered directly
to Modern, and thus, Modern owed him for their fair
value. Alternatively, he claims that he is entitled
to recover under a payment bond issued by the defendant
National Union Fire Insurance Company (National) to
Modern with respect to the project.
The
sole issue on appeal is whether the trial judge erred
in holding that the plaintiff sufficiently complied
with the notice requirement of G.L. c. 149, §
29, the payment bond statute, to permit recovery on
the bond. FN1 We think that in the particular circumstances
presented here the judge properly could conclude the
statutory notice and statement of claim requirements
of G.L. c. 149, § 29, were satisfied.
| |
FN1
At the jury-waived trial, the judge ruled in favor
of Modern on all counts. |
The
relevant facts are taken from the trial judge's findings
of fact. FN2 The plaintiff was engaged in February,
1990, by J.S.L. Corporation (J.S.L.), a subcontractor
to Modern on this project, to perform trucking and
hauling services. Upon completion of his work, he
submitted a bill to J.S.L. for $1,678.75. Shortly
thereafter, he received a check from Modern, made
payable jointly to J.S.L. and to him, for $1,580.
When he received the check, J.S.L. had already endorsed
it. The plaintiff deposited the check and then sought
to obtain the difference he was owed by notifying
both J.S.L. and Modern. The bookkeeper for Modern
told him that the company paid for hauling services
at the rate of $40 per hour, whereas he, Bastianelli,
had billed at $42.50 per hour. The plaintiff persisted
in his demand, and eventually Modern sent him a second
check for the difference of $98.75. This second check
initially was issued to the plaintiff and J.S.L. jointly,
but when J.S.L. refused to endorse it, another check
was issued to the plaintiff alone.
| |
FN2.
It has not been made to appear, nor has it been
argued, that the judge's findings are "clearly
erroneous." Mass.R.Civ.P. 52(a), 365 Mass.
816 (1974). |
In
June, 1990, the plaintiff did some more work for J.S.L.
on the same project. Upon completion, the plaintiff
sent an invoice for his work to Modern, made out to
J.S.L. in care of Modern. The daily time slips, which
were forwarded with the invoice, were all addressed
to J.S.L. Modern initially declined to pay the plaintiff,
taking the position that it had paid J.S.L. what J.S.L.
was due and that the plaintiff had to look to J.S.L.
for payment. A later offer by Modern to pay a compromise
amount was declined by the plaintiff.
The
judge correctly stated that G.L. c. 149, § 29,
"does not prescribe the form of the required
notice" and all that the claimant is required
to do is state with substantial accuracy the amount
claimed and the name of the party for whom the work
was performed.FN3 Concluding that the invoice accompanied
by the daily slips fulfilled this notice requirement,
the judge ruled that the plaintiff was entitled to
recover $1,955 from the surety company under its bond
and to reasonable legal fees. National appeals from
the ensuing judgment.
| |
FN3.
The judge stated that Modern "does not
dispute that it received the invoice and backup
material within the time period prescribed in
the statute." That statement is challenged
on appeal, but see note 2, supra. |
National
argues that the plaintiff did not comply with the
notice requirement of the statute because the invoices
sent by the plaintiff to Modern did not reasonably
put it on notice that the plaintiff was seeking recovery
from the general contractor under the payment bond
statute. See Cinder Prod. Corp. v. Schena Constr.
Co., 22 Mass.App.Ct. 927, 929, 492 N.E.2d 744 (1986).
There was no reversible error.FN4
| |
FN4.
As to a claim that the plaintiff failed to send
notice by registered or certified mail, it is
sufficient to say that "[i]f actual timely
notice is proved ..., failure to comply with
[such] requirement is not a fatal deviation
from statutory procedures." Cinder Prod.
Corp. v. Schena Constr. Co., 22 Mass.App.Ct.
at 929, 492 N.E.2d 744, and cases cited therein. |
The
defendant places principal reliance on Federal case
law to support its argument that invoices are not
sufficient to constitute notice. See United States
ex rel American Radiator & Standard Corp. v. Northwestern
Engr. Co., 122 F.2d 600, 602 (8th Cir.1941). However,
in that case, the claimant submitted the invoices
only to the subcontractor who, in turn, "appeared"
to have given them to the general contractor merely
for use in arriving at estimated payments which the
government was to make. A later Federal case, United
States ex rel. Blue Circle West, Inc. v. Tucson Mech.
Contracting, 921 F.2d 911, 914 (9th Cir.1990), is
likewise inapposite. Similarly, in a case cited by
the defendant, Barboza v. Aetna Cas. & Sur. Co.,
18 Mass.App.Ct. 323, 325, 327-328, 465 N.E.2d 290
(1984), the claimant's written notice to the general
contractor was not timely.
In
the circumstances of this case, where the general
contractor had previously paid the claimant directly,
had notice of the subcontractor's lack of cooperation,
received its own copy of the invoice (and daily time
slips) from the claimant, and offered a compromise
amount to the claimant, "[w]e cannot say the
judge's ultimate finding that the claim of notice
met the requirements of the statute 'is either clearly
erroneous or inconsistent with the relevant legal
standards.' " Worcester Air Conditioning Co.
v. Commercial Union Ins. Co., 14 Mass.App.Ct. 352,
357, 439 N.E.2d 845 (1982), quoting from Marlow v.
New Bedford, 369 Mass. 501, 508, 340 N.E.2d 494 (1976).
We
make one final comment. Given the amount of money
at stake ($1,955) and the fact of actual knowledge
by the general contractor, we ordinarily would consider
imposing sanctions on the appellant's attorney (see
Avery v. Steele, 414 Mass. 450, 457, 608 N.E.2d 1014
[1993]), but for his claim that the matter at issue
here is of great importance and genuine concern to
the construction bar.
Judgment
affirmed.
back to top
|