Boston Construction Law
Boston Construction lawBoston Construction lawBoston Construction lawBoston Construction lawBoston Construction lawBoston Construction lawBoston Construction lawBoston Construction law



Case Law
 

Below you will find a synopsis of some of the cases handled by our firm.
You may click on the citation of a particular case for a link to the full text of the Court's opinion.


Breach of Contract


C. Max, Inc. v. Cresta Construction et. al., 72 Mass.App.Ct. 1112, 891 N.E.2d 718 (Table), 2008 WL 3286507 (Mass.App.Ct.) (Unpublished Decision).


Prosecuted claims on behalf of a subcontractor per M.G.L. c. 149, §29 to Judgment and a full recovery of the subcontractor's contract balance as well as an award for legal fees. Successfully defended delay claims brought by the general contractor. Matter was fully affirmed on appeal.
See Decision


J.K. Glass, Inc. v. Jan Five Corp. d/b/a Alexandra Construction et al., Suffolk Superior, C.A. No. 01-0850-BLS (Business Litigation Session)


Prosecuted breach of contract, bond and mechanic's lien claims on behalf of a subcontractor on a private project to Judgment obtaining recovery of substantially all of the subcontractor's contract balance. Successfully defended alleged delay, extra work and incomplete work back-charges valued in excess of $1 Million brought by the general contractor.
See Decision/Aug 7th
See Decision/Oct 23d

Bad Faith of the Commonwealth


TLT Construction Corp. v. Commonwealth (D.C.P.O.), Suffolk Superior, C.A. No. 92-6572F

Judgment obtained against the Commonwealth for general contractor in the amount of $2,018,621, plus interest of approximately $800,000.

Additionally, a finding entered against the Commonwealth for sanctions per M.G.L. c. 231, §6F for insubstantial, frivolous and bad faith defenses, awarding 150% interest, legal fees and costs, totaling approximately $1 Million. See Decision

Chapter 149, §29


Bastianelli v. National Union Fire Ins. Co., 36 Mass.App.Ct. 367 (1994).

Interpretation of Public Construction bond statute finding that actual notice is sufficient to meet the statutory requirement for "written" notice under M.G.L. c. 149, §29.
See Decision



Chapter 30, §39F

Manuel F. Spencer & Sons, Inc. v. Commonwealth, 16 Mass.App.Ct 290 (1983).

First case in Massachusetts interpreting "extra work," as used in M.G.L. c. 30, §39F, the public works' subcontractor direct payment statute.

Also cited for interpretation of "business records exception" to hearsay (M.G.L. c. 233, §78).
See Decision

Chapter 30, §39N

Sutton v. MDC, 423 Mass. 200 (1996).

S.J.C. decision reversing Appeals Court decision (38 Mass.App.Ct. 764 (1985)).

First case in Massachusetts recognizing the federal concept of a so-called "Type II" changed condition in the work under M.G.L. c. 30, §39N.

Also cited for interpretation of the constitutional provision for the effective date of a new statute, c. 231, §6C and §6I, concerning interest on judgments against the Commonwealth.
See Decision

Chapter 93A, §11

TLT Construction Corp. vs. Tappe, 48 Mass.App.Ct 1 (1999).

Decision sustaining a general contractor's right to proceed under c. 93A against a public construction project architect for bad faith conduct, subsequent to recovering damages from a municipality, as determined by arbitration proceedings. See Decision


R.W. Granger & Sons, Inc. v. J&S Insulation, Worcester Superior Court, C.A. No. 92-1388 (affr'd 435 Mass. 66 (2001)).

After recovery on behalf of the subcontractor of some $410,245.83 in funds due on a public construction project (including interest and attorney's fees per M.G.L. c. 149, §29 and defeat of $500,000.00 in backcharges), a finding was entered for the subcontractor against the general contractor's surety for double damages and attorney's fees pursuant to M.G.L. c. 93A, §11 in the sum of $966,284.94, based on unfair and deceptive claim settlement practices.

Supreme Judicial Court of Massachusetts affirmed the decision of the Worcester Superior Court in 2001, allowing the subcontractor's recovery, including multiple damages and legal fees, against the general contractor's surety for the C. 93A violations. See Decision

back to top


home history services case law attorneys directions contact
56 Chestnut Hill Ave. Boston, MA 02135